Construction Update

Public road improvements continue, there may be a temporary increase in dust as the roads are cement stabilized and new rock is placed. Magnesium chloride will be used on critical areas to help reduce dust. Public road construction is scheduled to finish in July, with ongoing maintenance performed throughout the life of the construction period.

Trenching and cable installation will commence the first week of July.   

Over the next couple of months, expect to continue seeing large turbine components delivered to the construction site. Turbine components (tower sections, blades, and machine heads), and various cranes will begin to arrive mid-July. Concrete placement for foundations should be completed by mid-August.