September Construction Update

On Wednesday, September 14, local residents joined staff and project partners of Apex Clean Energy at Great Pathfinder Wind for a turbine blade–signing ceremony.

Construction on site continues, and the project remains on track to begin operating this winter. Below are some construction highlights:

  • Approximately 20% of turbines have been erected, and turbine deliveries are expected to be complete by November.
  • Workers are currently pouring foundations for the substation.
  • Underground collection is on schedule to be complete in October.
  • Transformer box pads have been installed.
  • Directional boring is complete.
  • Reclaim of tower sites has begun at fully erected turbines.
  • T-line work continues, with anticipated projected completion in November.